First I’ll give you ayksolutions events that occurred yesterday then I’ll give my input!
Let’s Begin: “At approximately 4:45 am EST the NAP suffered a power outage lasting approximately 10 seconds from Georgia Power.
The generators fired and came online 15 seconds after the initial outage and the load was transferred to generators which ran for 30 minutes while monitoring the incoming power quality from GA Power at which time the load was transferred back to utility.
One of the UPS’s that serves part of the facility suffered a battery outage on 2 different redundant strings which caused it to drop the load.
We installed a second redundant string approximately 9 months ago to minimize the possibility of this type of situation. The batteries in the 2 strings are setup in parallel meaning each is capable of carrying the full load for up to 5 minutes.
All it takes is 1 battery in a string to fail for the entire string to fail. This is the same in all ups systems and is the reason we installed the second string from advice from the manufacturer.
The original string batteries are 1.5 years old and were installed new. The second string is 9 months old and was installed new.
A single battery in the second string failed after 3 batteries in the first string failed.
We turned the generators back on to avoid an interruption during troubleshooting and maintenance and MGE sent a tech onsite within an hour to troubleshoot at which time we discovered the battery issue. We replaced the batteries within an hour of diagnosis and brought the system back online and out of maintenance bypass.
The load is currently protected and all batteries have been tested again.
Both sets of batteries have been maintained and tested by MGE direct service every 6 months under a pm plan that they recommended for proper maintenance and operation. This was extremely rare and unforeseen to have something like this happen.
We are purchasing our own battery tester and will set up a monthly pm on the batteries that we will conduct ourselves in addition to the 6 month pm that MGE does on the UPS as Well as the batteries. We are also researching a real time battery monitoring system that can predict battery failure.
Batteries are the weakest link in the system and we feel like we properly followed recommended engineering and maintenance on these systems. However that will not be assured 100% as we found out today in a very rare incident.
Extemporaneous events that continued to affect service during the outage:
One of the main metro e switches that runs the links of our backbone Went offline during the outage and during that power induced reboot we lost connectivity to half our backbones. We have our backbones split in half – with half going out the east and half out the West side of the building taking diverse paths across redundant switches to the final interconnect points.
The switch was unstable when it came back online due to a gbic that died and for some odd reason rebooted itself several times about every 10 minutes. We replaced the gbic with a spare we keep onsite.
This caused half the backbones to go up and down and placed a large cpu load on the different core routers We have due to bgp table loads going on – this is very cpu intensive and when you have a lot of up and down it can appear that the network is completely down (it is if you are on a link that is flapping) but the fact is that the entire network was not down but was impacted. This settled down when the switch was stabilized.
We split our backbones up over several different redundant backbone routers. Once this switch was brought back online and stabilized the network stabilized as well.
An access switch that serves 16 servers also died and we replaced it with a spare once we found the issue. We keep spares on site for every piece of network gear we have.
An apc that was only 6 months old and is a dual fed apc from 2 different power sources (including the newer ups) failed and did not come back – We replaced it with an onsite spare. It was bizarre to say the least and of course it powered one of our 3 main dns clusters so we lost dns capacity for an hour.
Most of the issues currently going on are related to server hardware that did not do well in a power reboot situation or need an fsck. We are actively working on them and will not rest until all is well.
Many customers in the facility do have A and B feeds from our power. We offer this through different ups systems / different power panels and different transformers. Some very early customers that purchased a and b feeds when we only had one ups system at the NAP are on the same ups and as such lost power. Those customers will be offered a free move on their b feed to the newer ups to increase their power diversity – they simply need to open a ticket.
What are we doing on power in the future?
We have another UPS from MGE on order as of 4 Weeks ago that is due to deliver in mid Feb that will increase the diversity of the power in the facility. We plan on having 2 battery strings on it as Well.
We are in the process of installing another set of 5 Cummins generators and another 3000 amp transformer which will further diversify our generator and transformer plant – this will be completed in mid February – construction of this is going on currently We took delivery of the switchgear and generators 2 Weeks ago. 4 ups/ will be moved to the new power feed and generators to diversify the power source to the UPS. This will give us 100% redundancy on the A / B feeds at that point.
We installed a redundant b feed to our metro e gear and 2 dual fed apcs at our TELX cabinet after TELX suffered a complete UPS failure at 56 Marietta 4 months ago. This turned out to be good because there was another complete failure of the B ups 4 Weeks ago – but We Were not affected since we had a redundant feed from them. The outage affected all customers on the second floor. We would have more than 50% of our network had we not been on dual fed apcs and dual power feeds at the building which would have been bad.
We are increasing the battery pm schedule to monthly from biannual.
We are researching a battery monitoring system for the strings.
We will be taking a fuel delivery this week to restock our main fuel supply
We are examining in depth on of our 4 core metro switch abnormalities this morning and if we do not find a RFO from the manufacturer will be examining replacing it or upgrading to a different more robust solution – which has been in our long term plan but may get moved up.
We will be doing another power examination of our core switching routers ( currently 6 of them all with dual fed power ) and our core metro e switches (currently 4 of them) to make sure that our power feeds are truly redundant and no legacy circuits are there to affect them.
We will be examining our on side spares inventory to make sure we are still at correct levels since we used some items this morning.
We apologize for the outage caused by the failure of the primary and backup batteries and will continue to provide the best service at an excellent price.
The MGE tech that has all the major accounts in Atlanta including coke and several others told us that this was a very freak occurrence with negligible odds of happening and in his opinion We have done everything right on our maintenance and pm and redundancy of the batteries and he would have done the same thing and that there was really nothing he would have recommended different at that point.
We are still going to make the changes above that I mentioned though.”
Confused yet? I sure was for the most part but reading it over a second time most of it made sense and I got the general overview of what happened…
Onto what happened when I got up @ 10:40am. I almost didn’t get up when the alarm went off but I figured I might as well cause its 10:40am now and I don’t wanna sleep all day… Go over to macbook type in password, disable alarm. See that I have about 8 ims from 4 different people.Wonder what they are about… Then my email comes up on the right top of my screen like it always does via gnotifier (and growl, google it if you don’t know what it is…). One of them is from ayksolutions saying something about being down. I’m then like WTF?! check my mail, click the forum post link, login, read the post.. FREAK OUT… Then look at the 4 customers who had continued to im me.. Replyed, with the post from the forum. Then sent ims to the other clients whom hadn’t im’ed me and were on msn. A couple others I emailed.
Once all that was done I played the waiting game.. 8 hours later I send in a ticket cause its been 8 FUCKING HOURS.. They respond 10minuets later asking for my ip and root pw. I get them the root pw cause the president replies with the ip. They look into it. Looks like a kernel issue. From my understanding after the power ubruptly went out there were some problems caused which led to the said problems. That took a couple more hours since they were busy working on other servers that had worse or the same type of issues. My buddy sully added them on msn for to try and get some updates out of them while I was afk. He did but when he left school to come home I added them and with whom I am thinking is artyom the president we fixed the problems together. Once the server was up there was a cPanel problem. In the past a service cpanel restart solves the problem. Not this time. Artyom then got me to update the cPanel information.. Nothing, then 30 minutes later Artyom figured out the problem. The date was incorrect which caused cPanel to think the server was trying to cheat the license.. It freaked out and said “FUCK YOU BUDDAH” and showed the error.. Then all was well again in server land. Been so ever since..
I’ll post here every once and a while when something happens, a page changes on the site or I just feel like it.. I’ll throw up a layout later on today.. It’s 11:45am and I need some lunch
– JoeM